We specialise in erecting and dismantling scaffolds for domestic, commercial and construction projects in Surrey and London | Free quotations
Project type: Scaffolding for access to windows, soffits and facias for painting.
Site location: Church Fields, Godalming, GU8.
Customer needs: This customer needed a structure around 4 sides of this large 2/3 storey property to paint all of the upper floor windows and the apexes. The scaffolding was approximately 180 linear metres with various returns and table lifts. This client was provided with a 4-week hire period within our price.
Obstacles and challenges we needed to resolve: We faced no problems erecting this structure as access to all sides of the building was pretty straightforward.
What we accomplished: Our scaffolders erected the following framework to provide safe access to 4 apex roof sections and dormer windows on various parts of the house.
We erected 2 lifts of scaffold around most of the perimeter of this property.
Front: This elevation of the property has several windows our customer needed to access the very top of. Our Surrey scaffolding erectors put up two scaffold platforms, both fully boarded with double handrails.
We then erected two table lifts to access another window and the top of the apex.
The left-hand side of the front of the building also returned slightly and required 2 lifts of scaffolding, plus a table lift to access another dormer window on the roof. This table lift was built by extending 8ft transoms as the roof steps in.
Sides: Both sides of this building were 2 lifts high and had hop-up lifts installed to reach the top of the gable ends. The right side of the property was a straight return from the front. The left-hand side hop-up was again erected using 8ft tubes as transoms and extending them into the roof.
Back: The back was a straight run with two lifts on the right-hand side. To the left was another apex roof with an additional dormer window setback. There was a large bay window below the apex, so we erected an 8.0-metre beam section placed above the 1st-floor windows. We again used 8ft transoms to throw into the roof area and create a small table lift to gain further access to the dormer that was setback.
Other information
Length of hire: A 4-week rental period was supplied to complete the painting works.
We are the go-to scaffolding company in Surrey and have built a great reputation and a large customer base who always come back to us. When you choose us for your scaffolding, you will be sure to get all of the below:
Our skilled teams of scaffolders have the experience and know-how to put up any type of scaffold required in Surrey. Here is a comprehensive list of the most common scaffolds we have previously erected:
The quickest way to get a price for your scaffolding is to fill out your details, upload images, and measurements if you have them, and we will be in touch with a quote via email or WhatsApp